Kashmir Chowk Underpass Islamabad: CDA Starts PKR 1.4 Billion Project
CDA says the Kashmir Chowk Underpass project has broken ground at an optimized cost of PKR 1.4 billion. The authority gives a one-month completion target, but this is a project target—not completed-work evidence or a property-price forecast.
Swipe or scroll through all 1 images. Official documents are unedited; planning concepts and contextual images are clearly labelled.
01FPN source summary • figures and timeline attributed to CDA's official release
Verified figures
CDA's published project snapshot
All figures below are attributed to CDA's 7 October 2026 release and remain subject to execution and later official updates.
Item
CDA statement
How buyers should read it
Finalized cost
PKR 1.4 billion
A public-project figure, not a property valuation
Current traffic
Approximately 107,000 vehicles at the junction
Authority-stated traffic volume, not a footfall or sales forecast
Road components
Dedicated underpasses and four new slip roads
Confirm the final traffic plan and operating routes after completion
Additional land
Approximately five acres for road infrastructure and facilities
The release does not provide parcel-level title or acquisition details
Completion
Targeted within one month
A target, not proof that the project is complete or open
Travel-time outlook
About 16–18 minutes after integration with upcoming road improvements
Forward-looking estimate dependent on wider network works
Buyer questions
Frequently asked questions.
Has the Kashmir Chowk Underpass opened?+
No. CDA's 7 October 2026 release records the foundation stone and a one-month completion target. It does not say the underpass is complete or open to traffic.
What does CDA say the project will cost?+
CDA states PKR 1.4 billion after reducing the initial PKR 1.6 billion estimate through cost optimization.
Does the project guarantee nearby property-price growth?+
No. The official release contains no transaction-price series, rental forecast or investment-return guarantee.
01
What CDA announced on 7 October 2026
CDA's official release says the Prime Minister laid the foundation stone for the Kashmir Chowk Underpass in Islamabad. The authority describes the scheme as a congestion-relief and road-connectivity project linking movements from Serena and Faizabad towards Murree and other relevant destinations.
02
Cost, traffic and planned road components
CDA says the finalized project cost is PKR 1.4 billion, reduced from an initial PKR 1.6 billion estimate. The release puts current junction traffic at about 107,000 vehicles and lists dedicated underpasses, four slip roads and approximately five acres for expanded road infrastructure and associated facilities.
03
Timeline and travel-time figures are targets
The authority targets completion within one month. It also says travel between Islamabad and Rawalpindi could fall to about 16–18 minutes after the project is fully integrated with planned expressway-lane expansion. FPN treats both statements as forward-looking authority targets rather than completed-work evidence.
04
Property buyers should avoid speculative pricing
Improved roads can affect accessibility, but this release does not prove a price increase for any sector, scheme, plot or commercial unit. Before relying on the project in a purchase decision, verify the exact location, legal access, title and authority record, on-ground completion, operating traffic plan, transfer status, dues and a dated comparable asking-price sample. Contact FPN on 0322-4222522 for a document-focused review.
Verification note
Verified 7 October 2026 against CDA's official dated release. CDA states that the project has been finalized at PKR 1.4 billion after cost optimization from an initial PKR 1.6 billion estimate; the junction currently handles about 107,000 vehicles; planned works include dedicated underpasses, four slip roads and roughly five acres for expanded road infrastructure; and the authority targets completion in one month. CDA also says integrated expressway improvements are expected to reduce Islamabad–Rawalpindi travel time to about 16–18 minutes. These are authority statements and forward-looking targets. The release does not establish physical completion, an exact opening date, land-title consequences, plot-wise access, property prices, rental returns or guaranteed appreciation. Information may change after publication; always obtain the latest official document before acting.